Task 1.2 & 1.3 COMPLETE ✅ Core knowledge base infrastructure: - activity_knowledge_base.json: Catalog of 8 activities with metadata - CloneRepoActivity: Clone Git repo (stable, 1 retry) - AnalyzeCodeActivity: AST analysis (flaky, 3 retries) - SecurityScanActivity: SAST scanning (2 retries) - GenerateReportActivity: Report generation (1 retry) - DeploymentPreCheckActivity: Pre-deployment validation (flaky, 2 retries) - NotifyStatusActivity: Slack/email notifications (flaky, 3 retries) - ApproveWorkflowActivity: Human approval (120m timeout) - ArchiveResultsActivity: Cloud storage archival (flaky, 2 retries) - knowledge_base.go: KnowledgeBase loader with methods: - LoadKnowledgeBase(path) - Load from JSON file - LoadKnowledgeBaseFromDefaultPath() - Auto-discover file - GetActivity(name) - Lookup single activity - GetActivityNames() - List all activity names - HasActivity(name) - Check existence - GetTimeoutForActivity(name) - Get timeout from KB - GetRetryPolicyForActivity(name) - Get retry config - IsFlaky(name) - Check if flaky - GetDependencies(name) - Get activity dependencies - ListActivitiesByCategory(category) - Filter by category - Validate() - Check for circular dependencies - PrintSummary() - Human-readable summary - knowledge_base_test.go: 14 unit tests - Test loading, lookup, filtering, dependencies - Test timeout/retry extraction - Test validation logic - All tests PASS ✅ (22/22 total) Acceptance criteria met: ✅ Knowledge base loads successfully ✅ All 8 activities properly defined ✅ Flaky/stable flags correctly set ✅ Dependencies validate with no cycles ✅ Timeout/retry extraction works ✅ Unit tests pass (14/14 KB tests) ✅ Ready for validator (Task 1.4) Effort: 5 hours (estimated 3+2) Files: activity_knowledge_base.json (10.3KB) knowledge_base.go (246 lines) knowledge_base_test.go (324 lines)
3.7 KiB
Poimen Routing Workflow - Implementation Progress
Last Updated: August 31, 2025
Current Phase: Phase 1: Foundation
Overall Progress: 1 of 27 tasks complete (3.7%)
PHASE 1: FOUNDATION (8-10 hours)
Task 1.1: Create Go Type Definitions ✅ COMPLETE
Status: COMPLETE
Completed: 2025-08-31
Hours Used: 2 hours
Effort Estimate: 2 hours
Deliverables:
-
✅
internal/routing/types.go(159 lines)- WorkflowSpec (one-time workflows)
- CronWorkflowSpec (scheduled workflows)
- State (Task/Pass/Fail)
- RetryPolicy, CatchClause
- ExecutionContext, ExecutionEvent
- PollParams, PollResult, Result
- ActivityMetadata, InputField, OutputField
- Constraints, Heartbeat
-
✅
internal/routing/types_test.go(286 lines)- 8 comprehensive unit tests
- JSON marshaling/unmarshaling
- Complex workflow scenarios
- All tests PASS ✅
Acceptance Criteria:
- ✅ All types compile without errors
- ✅ JSON marshaling/unmarshaling works correctly
- ✅ Unit tests pass (9/9 PASS)
- ✅ Ready for next phase
Commit: 05a150b1 - feat(routing): implement WorkflowSpec and CronWorkflowSpec types
Notes: Types are solid and flexible. Ready to proceed with Task 1.2 (ActivityKnowledgeBase.json)
Task 1.2: Create ActivityKnowledgeBase.json ⏳ TODO
Status: TODO
Effort Estimate: 3 hours
Blocker: None
What to build:
- ActivityKnowledgeBase.json with ~7-10 activities
- Each activity: name, description, category, inputs, outputs, constraints
- Include both flaky (retry 3x) and stable (retry 1x) activities
Task 1.3: Create ActivityKnowledgeBase Loader ⏳ TODO
Status: TODO
Effort Estimate: 2 hours
Blocker: Depends on Task 1.2
Task 1.4: Create WorkflowSpec Validator ⏳ TODO
Status: TODO
Effort Estimate: 3 hours
Blocker: Depends on Task 1.1 ✅
PHASE 2: LLM-ROUTER (12-15 hours)
Task 2.1-2.5 ⏳ TODO
Status: All TODO
Blocker: Waiting on Phase 1 completion
PHASE 3: ROUTINGWORKFLOW (15-18 hours)
Task 3.1-3.6 ⏳ TODO
Status: All TODO
Blocker: Waiting on Phase 1 & 2 completion
PHASE 4: API/CLI (12-15 hours)
Task 4.1-4.4 ⏳ TODO
Status: All TODO
Blocker: Waiting on Phase 3 completion
PHASE 5: TESTING (8-12 hours)
Task 5.1-5.4 ⏳ TODO
Status: All TODO
Blocker: Waiting on Phase 4 completion
PHASE 6: DOCUMENTATION (5-8 hours)
Task 6.1-6.4 ⏳ TODO
Status: All TODO
Blocker: Waiting on Phase 5 completion
SUMMARY
Completed: 1/27 tasks (3.7%) In Progress: 0 tasks Blocked: 0 tasks Remaining: 26 tasks (96.3%)
Phase 1 Completion: 25% (1 of 4 tasks done) Estimated Time to Phase 1 Done: 6-8 hours (by tomorrow) Estimated Time to All Done: 60-70 hours (3-4 weeks)
Current Velocity: 2 hours/task
Est. Daily Capacity: 8 hours/day
Est. Days to Completion: 8-10 days (assuming 1 engineer, 8h/day)
NEXT IMMEDIATE TASKS
Priority 1 (TODAY if possible):
- Task 1.2: Create ActivityKnowledgeBase.json (3h)
- Task 1.3: Create KB Loader (2h)
Priority 2 (TOMORROW):
- Task 1.4: Create Validator (3h)
- Phase 1 sign-off complete
Priority 3 (BEGIN Phase 2):
- Task 2.1: JSONPath Resolver (3h)
- Task 2.2: llm-router skeleton (2h)
BLOCKERS & NOTES
None currently. Types are solid and ready for next phase.
COMMITS THIS SESSION
| Commit | Message | Files |
|---|---|---|
| 05a150b1 | feat(routing): implement WorkflowSpec and CronWorkflowSpec types | types.go, types_test.go |
Status Indicator:
🟢 ON TRACK - Phase 1 started, Task 1.1 complete, no blockers